East Hartford's Road Projects 8/1-8/10
Weeks of 8/1-8/10, 2020
Posted on: July 31, 2020 - 1:10pm
East Hartford, CT - The Town of East Hartford has begun roadwork in the Cambridge Drive neighborhood, as part of the ongoing Road Improvement Program. Residents should expect a series of road improvements in the area over the next few weeks. Below is a list of roads that will be worked on for the weeks of August 1 through August 15, weather-permitting:
Week of August 1-August 8
- Reset of manholes on Nassau Lane and Milbrook Lane
- Handel Road - drainage work
- Nassau Lane - fine grading, manhole resents, as-built survey
- Milbrook - fine grading, mahole resets, as-built survey
- Various roads in the neighborhood - granite curbs, concrete sidewalk and ramps
Oxford Drive, Cambridge Drive, Princeton Lane- milling
Week of August 10-August 15
- Oxford Drive, Cambridge Drive - full depth section
- Nassau Lane - paving
- Milbrook Lane - paving
- Princeton Lane - full-depth excavation
- Oxford/Cambridge Drive - full-depth excavation
- Various roads - granite curbs, concrete sidewalk and ramps