MDC Construction Update - Cumberland Drive & Simmons Road

 Construction Update - Cumberland Drive and Simmons Road

CONSTRUCTION UPDATE
ROAD RESTORATION
Parking Restriction
Cumberland Dr. and Simmons Rd. – East Hartford 

Beginning Wednesday, July 5th, the Metropolitan District (MDC) and their contractor, Paramount Construction, will begin road restoration on Cumberland Drive.

This work is expected to take approximately 2-3 weeks to complete.

Approximate Dates / Planned Activity: 

7/5 – 7/7 : Milling Cumberland Drive
7/10- 7/12 : Milling Simmons Road
7/13-7/17 : Return to Cumberland Drive
7/17-7/20 : Final Paving – both streets

Construction Notes - Cumberland Drive & Simmons Road